Projects pipeline

Projects across SADC

Power, transport, mining, water and digital projects by stage, with sponsors, financiers and costs. Where the pipeline is thin, the gaps are the opportunity.

8 projects, $30.0bn of disclosed capital cost
ProjectCountrySectorStageCostSponsors and financiersExpected
Batoka Gorge Hydro-Electric Scheme
Joint project on the Zambezi below Victoria Falls. Feasibility, hydrology and climate studies are complete and both governments have committed equity; they are seeking private investors.
Zambia, ZimbabweEnergy
Hydropower
Planned–Government of Zambia, Government of Zimbabwe, Zambezi River Authority–
Hyphen green hydrogen and ammonia
Namibia’s flagship green hydrogen project near Lüderitz, targeting 1m tonnes of ammonia a year in phase one. Up to 15,000 construction jobs are projected.
NamibiaEnergy
Green hydrogen
Planned–Hyphen Hydrogen Energy, Government of Namibia, African Development Bank SEFA ($15.93m in grants)First-phase investment decision targeted for end-2027
Julius Nyerere Hydropower Station
Fully commissioned in August 2026 on the Rufiji River, taking Tanzania’s installed capacity to about 4,646 MW. Built by Arab Contractors and Elsewedy Electric; expected output about 5,920 GWh a year.
TanzaniaEnergy
Hydropower
Operating$2.8bnGovernment of Tanzania, Financed from domestic resources2026
Lobito Atlantic Railway rehabilitation
Rehabilitation of track, workshops, signalling and rolling stock on the Benguela line, the Angolan leg of the Lobito Corridor for Copperbelt copper and cobalt. Rail is expected to cut transit from about 45 days by road to under two days.
AngolaTransport
Rail and port
Construction$753.0mLobito Atlantic Railway concession (Trafigura, Mota-Engil, Vecturis), US DFC ($553m loan), Development Bank of Southern Africa ($200m)–
Mozambique LNG (Area 1)
Force majeure, declared in 2021 after insurgent attacks in Cabo Delgado, was lifted on 6 November 2025 and all work restarted in January 2026, with the project about 40% complete. The four-year halt added about $4.5bn to the cost.
MozambiqueEnergy
Liquefied natural gas
Construction$20.5bnTotalEnergies (operator, 26.5%), Mitsui (20%), ENH (15%), ONGC Videsh (10%), Beas Rovuma Energy (10%), BPRL Ventures (10%), PTTEP (8.5%)2029
Mphanda Nkuwa Hydropower
Downstream of Cahora Bassa on the Zambezi. In February 2026 the project moved from advisory to execution, with the AfDB backing EDM’s payment obligations and mobilising funds for transmission.
MozambiqueEnergy
Hydropower
Financing$4.5bnEDF, TotalEnergies, Electricidade de Moçambique, Hidroeléctrica de Cahora Bassa, African Development Bank (adviser, partial risk guarantee)–
TAZARA railway revitalisation
Launched on 20 November 2025. Upgrades track, bridges, stations, power and telecoms and adds about 34 locomotives and 760 wagons, cutting transit times by two-thirds. A direct competitor to the Lobito Corridor for Copperbelt exports.
Tanzania, ZambiaTransport
Rail
Construction$1.4bnChina Civil Engineering Construction Corporation (30-year concession)–
Zambia–Lobito rail link (greenfield)
New line to connect Zambia’s North-Western and Copperbelt mining areas to the Benguela railway in Angola, completing the Lobito Corridor. The Africa Finance Corporation leads development and fundraising.
Zambia, AngolaTransport
Rail
Planned–Africa Finance Corporation–